This is the first time I have done a glass deep processing enterprise. I want to ask how the monthly cost of glass deep processing enterprises is calculated. Specifically, thank you!

2 thoughts on “This is the first time I have done a glass deep processing enterprise. I want to ask how the monthly cost of glass deep processing enterprises is calculated. Specifically, thank you!”

  1. Hello: It can be allocated in the completion of the product and the product based on the cost incurred this month.
    . For example: Calculate 4mm glass:
    The direct material 10 this month, direct labor 6, manufacturing cost 4,4mm glass (4mm) completion entry cost 6, then
    6/(10 6 4) = 30%
    . The cost of completing the completion of the product is: direct material 10*30%= 3
    direct labor 6*3%= 1.8
    1.2
    The cost of the product should be: Direct Material 10-3 = 7
    Direct labor 10-1.8

Leave a Comment

Your email address will not be published. Required fields are marked *